Martin County commissioners will hold a public hearing October 13 to decide whether 396 acres near Kanner Highway qualify as an agricultural enclave under a new state law, one year after they unanimously rejected a plan to build homes on the same land. The property, known as Waterside, lies south of SW 96th Street between Kanner Highway and the St. Lucie River.
Kanner/96th Street Investments LLC has asked commissioners to certify the property under a Florida law that took effect July 1. Florida business records list The Kolter Group as the LLC's manager.
Commissioners voted 5-0 in November 2025 not to advance a request from the applicant to change the property's designation from agricultural to low-density residential. The new state law is meant for certain agricultural properties already surrounded by development or land planned for it. To qualify, an applicant must meet specific requirements involving the property's agricultural history, surrounding land, size and access to services such as roads, water and sewer. Whether Waterside meets those requirements is what commissioners must decide.
Commissioners can deny certification if the land does not qualify, but they must base their decision on the law's criteria, not simply whether they want homes built there. A denial requires written findings, which the applicant can challenge in court. If the county takes no action within 90 days of receiving an application, state law says the land must be certified.
Certification would not approve a subdivision. It would let the applicant later submit qualifying housing plans based on what is allowed on neighboring land. The law says those plans must be treated as an allowed use even if the county's existing growth plan or zoning would otherwise prohibit it.
Commissioners did not decide the Waterside request Tuesday. They unanimously approved fees for reviewing applications under the new law: $8,150 to review whether property qualifies and $16,600 to review development plans submitted later. Senior Planner Jenna Knobbe said the law puts staff on a tight schedule.
The county has 30 days to review a certification application and issue a report. A public hearing must follow within another 30 days. "We've kind of had to drop everything that we're working on and prioritize that application," Knobbe told commissioners Tuesday. The October 13 hearing is about whether Waterside qualifies for the new process, not approval of a housing site plan.